On many buildings the gutter sits away from the wall, so the downpipe has to step in to reach it. An offset does this. This guide explains how to build an offset from pipe bends, gives the pipe lengths for 70° bends, and covers fixing the downpipe brackets.

70°the usual bend angle for offsets
100mmfixed projection of the SOKN one-piece offset
1.5mcentres for pipe brackets
150mmfrom the top of the stack to the highest bracket

What is a downpipe offset?

The roofline, where the gutter is fitted, is commonly positioned away from the walls of the building. An offset arrangement connects the gutter outlet to the downpipe stack running down the wall.

Technical drawing of a downpipe offset from a gutter outlet to the wall, showing the projection U, the height H and the intermediate pipe length L between two bends
An offset: U is the projection, H is the height and L is the length of intermediate pipe.

The measurement U is the projection of the offset, which is the distance from the outlet to the wall. H is the height the offset takes up, and L is the length of intermediate pipe between the two bends.

Choosing the right offset

SOKN one-piece offset

Available with a fixed projection of 100mm. Choose it where the projection is exactly 100mm.

Bends and a pipe length

For larger projections, build the offset from pipe bends and a length of SROR pipe or an MST intermediate pipe cut down to the length you need.

Bend angles

Bends at 70° are typically used to create offsets. 85°/90° bends may be preferred for very long projections, but flow capacity is reduced.

Which bends to use

  • Use a BK conical bend at the top of the offset.
  • If the pipe has a spigot bottom, use a BK conical bend at the bottom of the offset as well.
  • If the pipe does not have a spigot bottom, use a BM or BKM pipe bend with socket at the bottom.

Offset pipe length table for 70° bends

Measure the projection U, find it in the first column, then read across for the height H and the length of intermediate pipe L. Use the table as an indication of the length of pipe needed.

U: projection (mm)H: height (mm)L: intermediate pipe (mm)
2202750
270290100
300300135
350320185
400340240
450355290
500375345
550395400
600410455
650430505
700450580
750465610
800485665
850505720
900520770
950540825
1000555880
1050575930
1100595985
11506101040
12006301090
Example: for a projection (U) of 450mm, the offset is 355mm high (H) and needs 290mm of intermediate pipe (L).

Fixing downpipe brackets

Fix pipe brackets at 1.5m centres. Fix the highest pipe bracket 150mm from the offset, or from the hopper head at the top of the stack. Use a spirit level or plumb line to line up the other brackets.

Pipe brackets are usually installed with screw-to-wall fixing or drive-in fixing. The choice depends on the construction of the building, the installer’s preference or regional convention.

  • SSVU universal pipe brackets suit either fixing method and have a click lock.
  • SVHA brackets are used on unpainted Rainline systems and have a wedge lock.
  • Drive-in fixing: snip off the fixing arms so the SST drive-in spike can be used. Drive-in spikes are ordered separately.
Technical drawing of a pipe bracket being screwed to a wall with a drill
Screw-to-wall fixing.
Technical drawing of a drive-in spike for a pipe bracket being hammered into the wall
Drive-in fixing: hammer the spike in.
Technical drawing of a pipe bracket being clicked closed around a downpipe on a drive-in spike
Drive-in fixing: close the bracket around the pipe.

Downpipe offset questions

What is an offset on a downpipe?

An offset steps the downpipe in from the gutter outlet to the wall. It is needed because the gutter often sits further out than the wall of the building.

What angle bends should I use to make an offset?

Bends at 70° are typically used. 85°/90° bends can suit very long projections, but flow capacity is reduced.

Is there a one-piece offset?

Yes. The SOKN one-piece offset has a fixed projection of 100mm. For larger projections, build the offset from pipe bends and a length of SROR or MST pipe cut to size.

How far apart should downpipe brackets be?

Fix pipe brackets at 1.5m centres, with the highest bracket 150mm from the offset or the hopper head at the top of the stack.

Which pipe brackets suit Rainline?

SSVU universal pipe brackets suit screw-to-wall and drive-in fixing. Unpainted Rainline systems use SVHA brackets.

Need help with an offset?

Shop downpipe fittings Request a quote

Next: learn about gutter brackets and fall, read the installation guide or browse the component guide.

↑